Improvement of the communication and remote control (SCADA) system for the OMVS interconnection / Felou project

Improvement of the communication and remote control (SCADA) system for the OMVS interconnection / Felou project

Date : 2012-12-28 / 2014-12-31
Montant total du projet : 581560.00 €
Client : SOGEM – Société de Gestion de l’Energie de Manantali
Financement : World Bank - IDA


false
2012-12-28T00:00:00+01:00
2014-12-31T00:00:00+01:00
PHASE I and II • 4 field visits: Manantali Kodialani, Nouakchott and Tobène • Determine hardware and software requirements in order to achieve inter-connections and power costs (telemetry, remote alarms, signalling); • Propose solutions and the necessary equipment in order to standardise the use of the fibre optic; • Analyse the existing system acquisition and management of data and determine the exhaustive list of data and tele-information exchange, • Analyse the existing system and propose updates to the SCADA / Manantali EMS in terms of technological developments and an acceptable quality / price ratio; • Analyse the options chosen for the future WAPP Centre of Information and Coordination (CIC) in terms of equipment, functions and acquisition / exchange of information; and identify priority facilities to implement at the Manantali dispatching stage to allow its short-term integration into the ECOWAS regional network; • Prepare tender documents and the relevant technical specifications. Phase III • Advise SOGEM with regards to evaluating bids from bidders and selecting one of the bidders; • Monitoring the implementation of the work
Dakar, Bamako
SOGEM – Société de Gestion de l’Energie de Manantali
SOGEM ACI 2000 Parcelle n° 2501 – BP E 4015, Bamako, Mali
World Bank - IDA
50.00
13
10.00
6
4
22.00
AETS
true